Access to Fairfield Energy's Oil and Gas Infrastructure
The infrastructure code of practice is a voluntary arrangement developed by Oil & Gas UK in consultation with DECC. Under the arrangement, operators have agreed to publish high level capacity, technical and commercial data about the pipelines and facilities that they operate on the UK Continental Shelf in order to facilitate the utilisation of such infrastructure, by prospective third party users, for the development of remaining UKCS reserves
Dunlin Area Infrastructure
The Dunlin Alpha is a fixed concrete gravity based installation, which lies within the East Shetland Basin of the Northern North Sea, serving as a manned production facility for the Dunlin and Dunlin South West fields. The installation stands in 151 metres of water, 506km North-North-east of Aberdeen in block 211/23a of the UK sector of the continental shelf (195km North East of Lerwick).
The installation is a four leg, concrete gravity base structure with a steel box girder based topsides supporting two levels of modules. The storage cell system in the GBS has been taken out of service and the platform has no storage capability
The platform has two process trains, a single three stage separation process for Dunlin (with two 1st stage separators), and the Osprey two stage process train for the subsea satellites . Nominal capacity of the respective trains are 165,000 blpd and 85,000 blpd respectively. Both trains have produced water separation facilities employing hydrocyclones. Associated gas from both trains is used for fuel gas, off gas from the second and third stages being feed to a single fuel gas compressor and thence to gas turbine generator sets. At present the platform is fuel gas deficient and power is imported from Brent Charlie via a 33kV power cable. During 2011 a 4” fuel gas pipeline is due to be laid between Thistle and Dunlin to provide a gas supply from the NLGP system. The power generation arrangements on the platform are to be upgraded as part of this project.
The Brent sequence fields in the Dunlin complex employ water injection as the primary means of pressure maintenance and secondary oil recovery. At present a number of platform wells have had ESP’s installed but there are no means of providing alternative means of artificial lift e.g. gas lift.
A total of 5 electrically driven water injection pumps are installed on the platform (2 nominally dedicated for subsea field pressure support) with a nominal capacity of 280,000 bwpd. This is currently limited by power generation and service water system constraints.
The platform is a pipeline node on the Brent system with connections to the Thistle and Murchison platform’s to the North and North East of the Dunlin location. The platform acts as the host for the subsea tiebacks of the Osprey and Merlin fields.
The Osprey subsea field is located 7km north-north-west of Dunlin in blocks 211/23a and 211/18a in a water depth of 159m and consists of 8 production wells and 4 water injection wells. Oil is produced via a subsea production manifold (PLBM), and transported through two 8" production lines contained within a 38" bundle carrier pipe to Dunlin Alpha. Osprey water injection is supplied by a 10" flexible via a central water injection manifold (WLBM) to the four satellite wells.
The Merlin subsea field is located 7km north-west of Dunlin Alpha in block 211/23a-b in a water depth of 150m. There are three production wells in a daisy-chain arrangement linked by a trenched and rock-dumped production pipeline to the Osprey production flowline risers via a crossover manifold situated 400m from Dunlin Alpha. A single Merlin water injection well is linked to the Osprey water injection pipeline by a flexible flowline via a Y-piece connecting spool.
Both subsea fields are operated from a common Aker Kvaerner subsea control system. Controls connections to the subsea field’s is via steel tube umbilicals.
The operation of the water flood on all three fields at relatively high water cut (>90% BS&W) means that the production trains for Dunlin and Osprey are currently within their nominal capacity, however the available effective operating capacity is not considered to be significant with the operators plans to increase production levels from the existing well stock.
Exported stabilised crude from the platform process (containing NGL) is commingled with oil from Murchison and Thistle for onward transmission to Sullom Voe (Shetlands) through the Brent System via Cormorant Alpha.
The following pipelines are connected to the Dunlin Alpha:
- 16-inch oil import from Murchison;
- 16-inch oil import from Thistle Alpha;
- 24-inch oil export via Cormorant Alpha into the Brent system;
- two 8-inch oil production from Osprey;
- 10-inch water injection to Osprey;
- 8-inch water injection to Merlin (via Y-piece connecting spool from Osprey WI line);
- 8-inch oil production from Merlin to Merlin crossover manifold.
In addition there is the 33Kv power cable which is connected to Brent Charlie. Availability of power supplies via this link is dictated by the ongoing capacity of the Brent Complex to export power. This capability will be lost as the decommissioning of this group of facilities proceeds.
The import and export risers are contained within platform Leg C. The Power cable and the future fuel gas riser are in Leg D. A number of 14” and 10” J tubes are available for use in Leg D. A number of low pressure rated large diameter lines (16” and 24”) are also available. The exact condition of the latter risers would need to be confirmed before potential use.
The operator has carried out studies on retrofit of additional riser systems not compatible with the available facilities and the most feasible means of adding riser capacity would be by means of catenary flexible risers or a riser ladder.
Export capacity in Brent system has to be applied for via the Brent system operator (TAQA). Capacity information for Brent system is available on the TAQA website.
5 Year Oil Ullage
5 Year Water Injection Ullage
5 year Gas Ullage
Note:
The Fuel gas import line is sized to provide a potential/nominal 10mmscfd flowrate export route. Export would only occur when the facility had excess gas after meeting its power generation requirement. This system is only due to be commissioned at the end of Q3 2011. Earliest date for gas export service would be dependent on third party entrant profiles.
Contact Details
Any interested parties should contact:
Dunlin Asset Manager
Fairfield Energy Limited, Pavilion 3, Kirkhill Business park,Howe Moss Drive, Kirkhill Industrial Estate, Kirkhill, Dyce, Aberdeen, AB21 0GD.info@fairfield-energy.com
Crawford
Fairfield holds 25% interest in the Crawford Oilfield, located in the Central North Sea. It holds almost 200 million barrels of Oil in Place.
Find out more
Glein
Fairfield acquired 50% of the Glein area which is located in Licence P1746 comprised of blocks 48/11c and 48/12b, and contains two undeveloped discoveries, Glein and Eos
Find out more
Operations
Fairfield has full or partial ownership of six assets within the North Sea, transforming discoveries into productive capacity.
Find out more
Decommissioning
Before decommissioning its fields, Fairfield will consult pro-actively with a wide range of stakeholders.
Find out more







